Our Sanctuary Renovations have been underway since August 2024.
TIMELINE
AUGUST 2024 – REMOVAL OF FURNITURE, PEWS, CARPET, & ITEMS NOT PART OF FINISHED SANCTUARY.
SEPTEMBER 2024 – REMOVAL OF 8,000 SQUARE FEET OF CEILING – 1/4 PLASTER & 3/4 ACOUSTICAL TILES. OLD INSULATION WAS REMOVED FROM ENTIRE ROOM.
OCTOBER 2024 – ELECTRICAL WIRING INSTALLED & INSPECTED.
NOVEMBER 2024 – SPRAY FOAM INSTALLED IN ENTIRE ROOF STRUCTURE CAVITY TO PREVENT INTRUSION OF HEAT & MOISTURE, AS WELL AS TO MAINTAIN COMFORT IN SANCTUARY.
DECEMBER 2024 – CEILING FRAMING PREPARED FOR INSTALLATION OF SOLID PINE CEILING ACROSS ENTIRE SANCTUARY.
JANUARY 2025 – PINE CEILING FINISHED WITH SEVERAL COATS OF PRE-STAIN, STAIN, AND CLEAR COAT FINISHES.
FEBRUARY 2025 – INSTALLATION OF APPROXIMATELY 1,500 PINE CEILING BOARDS
MARCH 2025 – OAK PANELS FINISHED WITH SEVERAL COATS OF PRE-STAIN, STAIN, AND CLEAR COAT FINISHES.
APRIL 2025 – INSTALLATION OF OAK PANELS AND SHEETROCK WALL BOARDS
MAY & JUNE 2025
INSTALLATION OF CHANCEL WITH PULPIT & COMPLETION OF NARTHEX ENTRANCE
INSTALLATION OF SANCTUARY LIGHTING & CEILING FANS
TRIM WORK
HVAC SYSTEM DUCTWORK CLEANED & SANITIZED
CARPET INSTALLATION
PEW INSTALLATION
SOUND SYSTEM, ORGAN, & PIANO INSTALLED
REMOVAL OF STAINED GLASS PICTURES IN VIOLATION OF 2ND COMMANDMENT (IMAGES) AND REPLACED WITH MATCHING ROSE FROM OTHER WINDOWS.